Multiphase pipelines · plant inlets · pressure equipment

The pipeline's shock absorber.

A wet-gas pipeline does not deliver a steady stream. Liquid collects in the low spots and then arrives all at once — a slug. The slug catcher is the big vessel, or the bank of big pipes, at the receiving end that swallows the slug, lets the gas go on, and meters the liquid out at a rate the plant can handle. This page explains it — and what an inspector looks at once one is in service.

The two designs ↓Ask a question
pipeline in:gas + liquid slugs inlet header dry gas out → to the plant liquid out, level-controlled fingers slope down toward the liquid end finger-type shown · vessel-type is one large horizontal drum doing the same job

What a slug is, and why it needs catching

Gas and liquid do not travel together politely in a long pipeline.

Terrain

Liquid pools in the low spots

Condensate and water settle in every dip along the line. When enough gas builds up behind a pool, it pushes the whole pool down the pipe as a plug of liquid. Hilly routes and long subsea lines make big ones.

Pigging

The pig sweeps the line

A pig run pushes every drop of liquid in the line ahead of it. That arrives at the receiver as one long slug — often the largest the receiving equipment will ever see, and the case it is usually sized for.

Rate changes

Ramp-up and start-up

Raising the gas rate sweeps out liquid that had been sitting at the lower rate. Start-ups and shut-ins do the same. The plant sees a surge it did not ask for.

The problem

Downstream can't take it

Inlet separators, compressors and treating units are sized for steady flow. A slug floods the separator, trips the compressor and carries liquid where it must not go. The slug catcher stands in front of all of that and takes the hit.

The two designs

Same job, two shapes. The choice is mostly about how much liquid has to be held and at what pressure.

Vessel-type

One large drum

gas liquid inlet device / baffle

A horizontal two-phase separator with a very large liquid section. The gas disengages across the top; the liquid pools in the bottom and is let down under level control. Internals — an inlet device, baffles, sometimes cyclonic tubes — improve the split.

SuitsModerate slug volumes, lower pressures, tight plots; simple to build and inspect as one vessel.
LimitWall thickness grows fast with diameter and pressure — big volume at high pressure gets heavy and expensive.
Finger-type (multiple-pipe)

A bank of big pipes

slope → liquid end

Several long, large-diameter pipes ("fingers") laid side by side on a slope between an inlet header and a liquid header. Gas separates in the first stretch and leaves through risers at the high end; liquid runs downhill and is stored in the fingers themselves until it is let down.

SuitsVery large slug volumes at high pressure — pipe wall is thin for its volume, and capacity is added by adding fingers or length.
LimitTakes a lot of ground, a lot of welds and a lot of supports; slope and settlement matter for the rest of its life.

A third arrangement, the parking loop, is a length of pipeline looped back on itself that holds the slug and drains it slowly — effectively a one-finger catcher built from line pipe. It is treated as pipeline.

How they're built

A slug catcher is pressure equipment first and a process unit second. The design basis decides which rulebook it lives under.

  • Vessel-type units are shop-fabricated pressure vessels: ASME Section VIII, stamped, with a data report that follows the vessel for life.
  • Finger-type units are built from pipe and fittings. Depending on the owner's design basis and the jurisdiction, they are designed either as piping to ASME B31 or as a pressure vessel to Section VIII — and that decision sets the inspection code later.
  • Wet sour gas drives the materials: sour-service steel, hardness limits and PWHT where the service calls for it, and corrosion allowance sized for the liquid that will sit in the bottom.
  • Sizing starts from the largest expected slug — usually the pig-run case — plus the liquid rate the downstream plant can accept, which sets the buffer volume and the slope.
  • Fingers ship as long spools; the field work is the headers, the tie-ins and the supports, so field welds and settlement surveys are part of the record from day one.
In the shop

Where the ITP earns its keep

Material certs against the design, fit-up and weld inspection on every finger and header, NDT to the code percentage, PWHT charts, hydrotest and the final data package — every hold point in order, signed by the person who actually witnessed it. That is exactly the traveler a slug catcher needs, and it is exactly what AssetSentry™ ITP builds out for the shop. Its built-in templates include an ASME vessel / slug catcher plan.

Code references: ASME Boiler & Pressure Vessel Code Section VIII; ASME B31.3 / B31.8; API 510 and API 570 for in-service inspection.

Inspecting one

Big, wet, cyclic and outdoors. Slug catchers collect most of the damage mechanisms a gas plant has.

Which code

API 510 or API 570

A vessel-type unit is an API 510 vessel. A finger-type unit is inspected under 510 or 570 according to how it was designed and registered — check the record before you plan the inspection, not after.

Bottom of line

Corrosion where the water sits

Water and CO₂ or H₂S lie in the bottom of every finger and the low end of every drum. Thickness at the 6 o'clock position, at the liquid end and at the headers is the number that decides remaining life. Measure it on a grid, not at one spot.

Top of line

Condensation corrosion

Cooling wet gas condenses on the crown of the pipe. Top-of-line attack is easy to miss from the outside and shows up as pitting at 12 o'clock — UT the crown as well as the bottom.

Erosion

Inlet header and first tees

Sand, scale and black powder arrive with the slug at velocity. The inlet header, the first fitting on each finger and any inlet device take the wear. Look for wall loss opposite the flow.

Fatigue

Slugs hammer the supports

Every slug is a moving mass. Support welds, saddle attachments, small-bore connections and riser tie-ins see the cycles. MT or PT the toes; check the supports for movement, corrosion under the saddle and lost slope.

CUI

Under the insulation and coating

Long insulated or coated runs at low elevation are corrosion-under-insulation territory. Strip and look at the low points, the supports and anywhere water gets in and stays.

Internals

Vessel-type: inlet devices and baffles

Inlet devices, baffles, vortex breakers and any cyclonic internals get erosion, fouling and cracked attachment welds. Open the manway and check them; carryover downstream is the sign they are failing.

Shutdown

What to do when it's open

Clean out the solids, UT the low points and crown on a grid, RT or UT the field welds you have never looked at, MT the attachments, and put the readings on the equipment record so the corrosion rate is real, not assumed.

The math

Remaining life, computed

t-min from the design code, corrosion rate from measured thickness over time, remaining life and the next interval from those — done from the readings, on the record, checkable by the next person.

Ask a question

About slug catchers, about inspecting one, or about this name. It goes privately to the owner of this site.

Nothing you send is published, and no phone number or email is shown on this page.
Sent — thank you.